
Excavation for the base of the new toilet block is now underway and we are aiming for it to be installed during May.
The modular unit is complete and awaiting transport from the manufacturer. As you can see in one of the photo’s the service area of the unit is ready for connecting when it arrives onsite.
Delays have been experienced due to the identification of a fire hydrant. It has transpired though that when contractors working on behalf of SWW attended to move the high pressure water main, the pipe system was dry and had been cut off a number of years ago.
Once the unit is in place the connections can be arranged. As this involves the utility companies (Gas, Water and Electric) we are tied to their deadlines and these can take between 4 to 8 weeks once the unit is installed. We have made it clear to them the importance that this unit is operational before the main Summer season.
The public toilets at Goodrington North and South remain open and operational. These facilities will continue to be cleaned and maintained by Healthmatic under the terms of the contract
If there are any issue with the current facilities please communicate directly with Healthmatic on their 24 hour Service Line 01249 823143.
News archive
- October 2025 (8)
- September 2025 (11)
- August 2025 (8)
- July 2025 (17)
- June 2025 (15)
- May 2025 (19)
- April 2025 (7)
- March 2025 (17)
- February 2025 (6)
- January 2025 (13)
- December 2024 (9)
- November 2024 (27)
- October 2024 (21)
- September 2024 (17)
- August 2024 (7)
- July 2024 (24)
- June 2024 (8)
- May 2024 (25)
- April 2024 (19)
- March 2024 (17)
- February 2024 (16)
- January 2024 (14)
- December 2023 (14)
- November 2023 (30)
- October 2023 (21)
- September 2023 (22)
- August 2023 (18)
- July 2023 (17)
- June 2023 (14)
- May 2023 (11)
- April 2023 (9)
- March 2023 (36)
- February 2023 (22)
- January 2023 (26)
- December 2022 (18)
- November 2022 (24)
- October 2022 (9)