End date weeks away for Torquay harbourside improvement works, but a road closure is needed to complete remaining significant works.
Torbay’s first major Town Deal funded improvement scheme is just weeks away from completion. Residents and businesses are advised that a six and half week road closure is now needed to complete the remaining phases of work in time for the Bay of Lights Illumination Trail.
From Tuesday 15 October until Friday 29 November, no traffic will be able to pass through the Strand (Fleet Street car park exit junction to Clock Tower).
Two separate road closures, totalling 10-weeks were part of the original programme of works. Working with the contractor and the local business community, the programme of works was re-phased, and the road closure elements delayed supporting Torbay’s vital visitor economy over the summer months.
The final phases have been amalgamated to recover much of the time lost on the project. Unexpected delays in earlier phases due to the discovery of utilities and a scheme redesign had added extra time onto the project. The amalgamation also reduces the length of time the road needs to be closed to motorists and public transport providers.
We do understand there is not an ideal time to close the road, but the project has reached a critical point, and the closure is necessary to get the project finished, the contractor demobilised and the area fully open again.
Access will remain to:
- Fleet Walk car park from Cary Parade (access also available via Rock Road).
- Victoria Parade and Beacon Quay can continue to be accessed via Torwood Street, but traffic control will be in operation 24-hours a day.
- Marina car park and most on-street car parking along Torbay Road will be unaffected by the road closure.
Businesses in and around the area will remain open as usual, with motorists advised to plan their route and parking location in advance of heading to the area.
The last major pieces of work will be carried out along Cary Parade (arcade side), at the Fleet Street / Strand junction, and at the Torwood Street / Victoria Parade junction. This work will see large areas dug up, allowing for junction reconfiguration, and signal and lighting infrastructure to be installed, before final resurfacing and lining work takes place. Work will also be taking place along the central strip of the Strand.
A fully signed diversion route will be in place to guide motorists around the closure. The diversion route will include parking suspensions in some areas to help larger vehicles navigate the route. Some aspects of the diversion route (Parkhill Road) will be clearly signed that the route is not suitable for large vehicles. Instead, they should continue to use Torwood Street to access Victoria Parade and Beacon Quay.
The closure will have a significant impact on buses, as services will not be able to travel through Fleet Street or the Strand and bus stops on both sides of Cary Parade and along Fleet Street will be temporarily closed. Revised and replacement routes for all affected services operated by Stagecoach and Torbay Buses and temporary bus stop locations will be confirmed over the coming days.
Taxi passengers can continue to find taxi ranks on Vaughan Road, lower Fleet Street, Torwood Street and Victoria Parade. Advice for taxi passengers is to head to the rank that is in the direction you would like to travel in to avoid additional fares. For example, if wanting to travel towards Babbacombe, to use the ranks on either Torwood Street or Victoria Parade. If travelling towards Paignton, to use the rank on Vaughan Road.
Safe pedestrian access will be maintained throughout the closure period.
Cllr Chris Lewis, Deputy Leader and Cabinet Member for Place Development and Economic Growth, said; “I’d like to thank the community, particularly the business community for their input and support for our first major Town Deal improvement project. We do know that at times it has been difficult and where we have been able to, we have made changes to the programme of work to minimise disruption and support businesses.
“We are now approaching the end of the project and whilst this is great news, we do now have to implement the road closure element. The road closure stretches from the exit of Fleet Walk car park on Cary Parade to the Clock Tower. Motorists can still access all car parks in the area, but they will need to ensure they enter the area from the right direction. Businesses remain open and with October half-term just weeks away, it is important that together we share that message.
“We have been able to reduce the amount of time that the road is closed from ten weeks, over two separate closures, to a single road closure period of six and half weeks.
“We must get this scheme finished in time for the Bay of Lights Illumination Trail which starts on Friday 29 November. We have a fantastic opening night planned which will be focused on the new public realm space.”
Ongoing advice for accessing the harbourside.
- All businesses and car parks are open as usual.
- Walk, cycle or travel by bus into the area where possible.
- On your approach to the harbourside, follow the signs to the nearest car park, or use on-street parking.
- If travelling from the sea front / Paignton direction, use Shedden Hill or Fleet Walk car parks.
- If travelling from Babbacombe, use Harbour, Beacon Quay or Meadfoot Road car parks.
The Strand public realm project is the first of three major Torquay harbourside regeneration projects that have been made possible after we secured £21.9million of Town Deal Funding to deliver the Torquay Town Investment Plan.
News archive
- October 2024 (2)
- September 2024 (17)
- August 2024 (7)
- July 2024 (24)
- June 2024 (8)
- May 2024 (25)
- April 2024 (19)
- March 2024 (17)
- February 2024 (16)
- January 2024 (14)
- December 2023 (14)
- November 2023 (30)
- October 2023 (21)
- September 2023 (22)
- August 2023 (18)
- July 2023 (17)
- June 2023 (14)
- May 2023 (11)
- April 2023 (9)
- March 2023 (36)
- February 2023 (22)
- January 2023 (26)
- December 2022 (18)
- November 2022 (24)
- October 2022 (18)
- September 2022 (13)
- August 2022 (15)
- July 2022 (22)
- June 2022 (14)
- May 2022 (35)
- April 2022 (23)
- March 2022 (32)
- February 2022 (18)
- January 2022 (14)
- December 2021 (22)
- November 2021 (22)
- October 2021 (25)
- September 2021 (23)
- August 2021 (18)
- July 2021 (26)
- June 2021 (24)
- May 2021 (21)
- April 2021 (21)
- March 2021 (33)
- February 2021 (30)
- January 2021 (27)
- December 2020 (24)
- November 2020 (37)
- October 2020 (29)
- September 2020 (27)
- August 2020 (22)
- July 2020 (37)
- June 2020 (38)
- May 2020 (39)
- April 2020 (36)
- March 2020 (22)
- February 2020 (10)
- January 2020 (18)
- December 2019 (7)
- November 2019 (11)
- October 2019 (15)
- September 2019 (16)
- August 2019 (8)
- July 2019 (9)
- June 2019 (7)
- May 2019 (16)
- April 2019 (11)
- March 2019 (11)
- February 2019 (7)
- January 2019 (11)
- December 2018 (11)
- November 2018 (14)
- October 2018 (14)
- September 2018 (9)
- August 2018 (7)
- July 2018 (19)
- June 2018 (21)
- May 2018 (7)
- April 2018 (10)
- March 2018 (35)
- February 2018 (9)
- January 2018 (15)
- December 2017 (9)
- November 2017 (17)
- October 2017 (11)
- September 2017 (6)
- August 2017 (7)
- July 2017 (13)
- June 2017 (22)
- May 2017 (16)
- April 2017 (8)
- March 2017 (9)
- February 2017 (9)
- January 2017 (4)
- December 2016 (10)
- November 2016 (11)
- October 2016 (14)
- September 2016 (9)
- August 2016 (10)
- July 2016 (11)
- June 2016 (4)
- May 2016 (20)
- April 2016 (14)
- March 2016 (18)
- February 2016 (8)
- January 2016 (15)
- December 2015 (13)
- November 2015 (19)
- October 2015 (17)
- September 2015 (8)
- August 2015 (6)
- July 2015 (19)
- June 2015 (11)
- May 2015 (20)
- April 2015 (14)
- March 2015 (15)
- February 2015 (13)
- January 2015 (17)
- December 2014 (17)
- November 2014 (18)
- October 2014 (14)
- September 2014 (17)
- August 2014 (16)
- July 2014 (10)
- June 2014 (8)
- May 2014 (1)
- February 2014 (1)
- January 0001 (1)