Essential works to rebuild part of Goodrington Road in Paignton start on Monday 22 January 2024 and will take up to 12 weeks.
This means sections of Goodrington Road will be closed to vehicles between Davies Avenue and Grange Road at the Dartmouth Road end.
The work will be in two phases to maintain access to Palm Tree View for vehicles and deliveries.
Phase 1 will be between Palm Tree View and Grange Road and will take up to seven weeks.
Phase 2 will be between the entrance to the Beverley Bay Holiday Park and Palm Tree View and will take up to five weeks.
The work has been delayed several times to avoid conflict with the Inglewood roadworks in the area. But it cannot wait any longer as the section of road is badly worn.
Because of the way it is made, the road will have to be completely renewed.
This means digging out just under half a metre of the carriageway, removing the waste, and rebuilding the road followed by surfacing.
During the works, the road will need to be under a 24-hour closure including at night.
This is because of the type of work taking place and for the safety of workers and road users. Footpaths will always remain open for pedestrians.
A diversion route will be in place on local roads while the work takes place and will be clearly signed.
Residents in the affected sections will not be able to drive onto the front of their properties and will need to park nearby during the period of the works.
The project has been planned for the quietest time of the year to have the least impact on the holiday parks and they will have full access.
Cllr Adam Billings, Cabinet member for Pride in Place, Culture & Events, and Parking, said: "There is never a good time for roadworks, but these essential works involve a major rebuild to improve this important route and cannot be delayed any longer.
"We have worked hard to keep the disruption to a minimum and we thank residents and road users for their patience and understanding during this period."
This work is part of Torbay Council’s annual infrastructure improvements and maintenance for 2023/24.
It is being carried out by SWISCo on behalf of Torbay Council with our sub-contractor Cormac Contracting Ltd.
More information including maps showing the works and diversion routes can be found on the Goodrington Road Reconstruction page on our website.
Additional resurfacing during these works is being funded from an extra £230,000 awarded to Torbay Council this year by the UK Government for local highways maintenance.
News archive
- October 2025 (17)
- September 2025 (11)
- August 2025 (8)
- July 2025 (17)
- June 2025 (15)
- May 2025 (19)
- April 2025 (7)
- March 2025 (17)
- February 2025 (6)
- January 2025 (13)
- December 2024 (9)
- November 2024 (27)
- October 2024 (21)
- September 2024 (17)
- August 2024 (7)
- July 2024 (24)
- June 2024 (8)
- May 2024 (25)
- April 2024 (19)
- March 2024 (17)
- February 2024 (16)
- January 2024 (14)
- December 2023 (14)
- November 2023 (30)
- October 2023 (21)
- September 2023 (22)
- August 2023 (18)
- July 2023 (17)
- June 2023 (14)
- May 2023 (11)
- April 2023 (9)
- March 2023 (36)
- February 2023 (22)
- January 2023 (26)
- December 2022 (18)
- November 2022 (24)