Future High Streets Funding Reallocations Updates

02/04/2026 - Future High Streets Funding Reallocations Updates

i)       that the overall project budget and Future Highstreet allocation for the Station Square project be reduced by £1,973,575 resulting in a new total budget of £973,283 required to fund the works to date.

 

ii)      that the overall project budget and Future Highstreet allocation for the Torbay Road project be uplifted by £113,363 resulting in a new total budget of £381,525 required to deliver the street scene enhancements.

 

iii)    that the Future Highstreet allocation for the Crossways project be increased by £1,860,212 resulting in a new total FHSF allocation of £4,626,109 to ensure compliant spend the grant.