Brokenbury Solar Farm
17/04/2025 - Brokenbury Solar Farm
1. That Cabinet recommends to Council:
That the following decision of Council made on 18 July 2024 be rescinded:
‘that up to £2,750,000 of prudential borrowing be approved subject to securing a unit rate per MWh that exceeds the loan repayments, covers projected maintenance and other operational and equipment replacement costs and provides an appropriate surplus per annum over the life of the scheme commensurate with level of risk.’
2. That the following decision of Cabinet made on 11 June 2024 be rescinded:
‘that the Chief Executive in consultation with the Leader of the Council, Finance Director and Cabinet Member for Finance should review and agree the final business plan after the EPC tender and Power Purchase Agreement (PPA) stage are complete and subject to that agreement is then authorised to agree and finalise the detailed terms and enter into contract with South West Water (SWW) or another purchaser of the electricity.’; and
3. That subject to 2. above authority be delegated to the Director of Finance, in consultation with the Cabinet Member for Place Development and Economic Growth, to agree and finalise the detailed lease terms, in line with an independent market valuation, and enter into a long lease for the land edged red as set out in Appendix 1 to the submitted report.
Contact Governance Support
- Email: governance.support@torbay.gov.uk
- Tel: 01803 207087
- Fax: 01803 207112
- Torbay Council
Town Hall
Castle Circus
Torquay
TQ1 3DR
- Brixham Town Council
- Budget digest
- Calendar
- Civic Mayor
- Committees
- Constitution
- Councillors' allowances
- Councillors' behaviour, interests and standards
- Decisions
- Decision lists
- Forward plans
- Get involved and have your say
- How the Council works
- Independent remuneration panel
- Meetings
- Outside bodies
- Overview & Scrutiny
- Search documents
- Subscribe to updates
- What's new
- Your Councillors
- Your MPs
- Become a Councillor