2011/0395/MPA - Totnes Road Service Station, site adj 141 Totnes Road, Paignton

Meeting: 22/08/2011 - Development Management Committee (Note - this committee was replaced by the Planning Committee from 6/5/19) (Item 222)

2011/0395/MPA - Totnes Road Service Station, site adj 141 Totnes Road, Paignton

Minutes:

The Senior Planning Officer explained that further to the meeting of the Development Management Committee held on 31 May 2011, where the above application was considered, the Section 106 Agreement had not been completed by the required date.  The Senior Planning Officer further explained completion of the Section 106 Agreement was imminent and sought members’ approval for an extension of time for one month.

 

Resolved:

 

That the Section 106 Agreement be completed by 22 September 2011.