Decision details

Capital Plan Updates - April 25

Decision Maker: Director of Finance

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Pavilion:

·         For the project to progress with the delivery of the opening up works via the competitively tendered supplier, utilising an overall budget of £1.5m from its £2m allocation of Towns Deal funds;

·         Subject to the Ministry of Housing and Local Government (MHCLG) approval, virement of the residual £500,000 to support other Towns Deal projects; and

Station Square:

·         For the project to progress through to delivery with a revised budget of £3,459,021 (£500,000 increase), utilising £500,000 of funding reallocations from Paignton & Preston Levelling Up Partnership (LUP) funding, subject to MHCLG approval.

 

 

Reasons for the decision:

All projects were reviewed and deemed to be strategically advantageous and satisfactorily compliant in terms of their feasibility and levels of risk to enable them to progress.

 

Alternative options considered:

Approval of this decision enables the projects to progress within a controlled process, minimising the risk of not fully utilising the grant funding available.

 

Implementation:

This decision will be implemented immediately.

 

Information:

Updates to the Capital Investment Plan following satisfactory review of business cases for the following projects:

 

·         Pavilion (Full Business Case)

·         Station Square (Revised Full Business Case)

 

Interests and Nature of Interests Declared:

None.

Publication date: 24/04/2025

Date of decision: 24/04/2025