Funding Allocation - Pavilion, Torquay
Decision Maker: Director of Finance
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
That the project progresses with the opening up works package and £1,607,200 be allocated to the Pavilion project.
That delegation of authority be given to the Director of Regeneration to the value of £500,000 as a risk budget to support any urgent structural and Health and Safety issues which may occur.
Reasons for the decision:
To proceed with the project and carry out the opening up works utilising an increased budget of £1,607,200.00
Alternative options considered:
Background documents: The Pavilion Project Initiation Document dated
2 August 2024
Implementation:
This decision will be implemented immediately.
Information:
The Project Initiation Document, (PID), for the Pavilion project was considered by the Capital and Growth Board at the meeting held on the 12 September 2024.
The initial PID only covered the design fees elements as per a standard project requirement. The current approved PID had value of £485,200 that covered, feasibility, concept design, detailed design, technical design and contingency, with the £500,000 risk budget being made available subject to a formal request for its draw down.
Following the feasibility exercise, the project is ready to progress onto the opening up works package inclusive of the construction management activities. To carry out the next stage an additional £637,000 is being requested.
In addition to the identified budget above a £500,000 risk budget is also being requested with delegation of authority afforded to the Director of Regeneration to utilise on the project should any structural and/or Health and Safety remedial actions be required during the opening up works.
Therefore, the total funding allocation approval being sought is £1,607,200
The funding will be allocated from:
· Approximately £500k Town Deal funds. (subject to finalisation of figures and final agreement with Ministry of Housing, Communities and Local Government (MHCLG)); and
· £1,107,200.00 Lease surrender monies from MDL.
Interests and Nature of Interests Declared:
None.
Publication date: 14/03/2025
Date of decision: 11/03/2025
Contact Governance Support
- Email: governance.support@torbay.gov.uk
- Tel: 01803 207087
- Fax: 01803 207112
- Torbay Council
Town Hall
Castle Circus
Torquay
TQ1 3DR
- Brixham Town Council
- Budget digest
- Calendar
- Civic Mayor
- Committees
- Constitution
- Councillors' allowances
- Councillors' behaviour, interests and standards
- Decisions
- Decision lists
- Forward plans
- Get involved and have your say
- How the Council works
- Independent remuneration panel
- Meetings
- Outside bodies
- Overview & Scrutiny
- Search documents
- Subscribe to updates
- What's new
- Your Councillors
- Your MPs
- Become a Councillor