Decision details

Turnkey Acquisition of "Scheme 1" of the Hotels to Homes Programme

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To proceed to conditionally exchange contracts for the turnkey acquisition of the completed units, with completion of the acquisition to take place once the relevant conditions have been met.

Reasons for the decision:

·         To meet the objectives set out in the 11 September 2024 Cabinet Paper.

·         To increase the supply of affordable housing.

·         To utilise the grant funding secured by Torbay Council specifically for this project.

·         To enable the Council to progress to the next and subsequent schemes.

Alternative options considered:

·         As set out in Section 5 of the Cabinet Paper.

 

Implementation:

Conditional Exchange of Contracts 4 November 2024

Information:

The turnkey acquisition of “Scheme 1”, as outlined in the Report to Cabinet of 11 September 2024 (and associated Exempt Appendices), being the first scheme of the “Hotels to Homes” programme.

Interests and Nature of Interests Declared:

None known.

Publication date: 06/11/2024

Date of decision: 30/10/2024